Work done since the last report were:
- Completion of the ground beams for the Shrine Hall and the TNB building
- Casting of mass concrete block in the Shrine Hall as foundation for the Buddha's image
- Backfilling and compaction to elevate the floor of Shrine Hall to about 1.2m above the surrounding.
- General earthwork.