Monday, October 5, 2009

Work Progress as on 30th Sept 2009

Work on site was generally slow. Progress at the end of September was about 10%. However, the Contractor was confident that the Project could be completed on time.

Work done since the last report were:
  • Completion of the ground beams for the Shrine Hall and the TNB building
  • Casting of mass concrete block in the Shrine Hall as foundation for the Buddha's image
  • Backfilling and compaction to elevate the floor of Shrine Hall to about 1.2m above the surrounding.
  • General earthwork.