Roof tiles for the Shrine Hall was delivered in early March and laying of the roof tiles commenced subsequently. The progress of the laying of the roof was about 80% completed.
Sample floor tiles had been submited for approval on 31st March.
TNB substation was completed with the doors and the windows installed.
Overall progress was about 65%.