The Work Progress as at 31st May 2010


The Contractor had completed laying of the aluminium foil underneath the tiled roof inside the Shrine Hall in preparation for the construction of the plaster ceiling.


All lighting locations were finalised, The wiring and lighting points were installed based on the Interior Designer's proposal.

The Contractor commenced installation of the external ceiling of the Shrine Hall and was completed before the endof the month.



The structure for the Buddha Image altar was constructed and awaiting finishing work to commence.




The infra- structure work comprising the road, car park and fencing was still progressing and was about 40% complete. The progress in the infra-structure work was still affected by the housing developer's water pipeline.

The overall progress was about 70%