- Completed the construction of columns and the tie-beams of the Shrine Hall.
- Assembled formwork and steel reinforcement for the roof-beams of the Shrine Hall and currently awaiting concrete to be cast.
- Construction of the floor slab and cable trenches in the TNB sub-station had been completed. The Contractor had also completed assembling the formwork and steel reinforcement for the columns, which currently awaiting to be cast.
- General site excavation to finished ground level was in progress.
Sunday, November 8, 2009
Work in Progress as on 31st October 2009
The work progress on Site for the first phase since the previous reporting was about 25%. The work carried out during this period were as follows: