Sunday, November 8, 2009

Work in Progress as on 31st October 2009

The work progress on Site for the first phase since the previous reporting was about 25%. The work carried out during this period were as follows:
  • Completed the construction of columns and the tie-beams of the Shrine Hall.
  • Assembled formwork and steel reinforcement for the roof-beams of the Shrine Hall and currently awaiting concrete to be cast.
  • Construction of the floor slab and cable trenches in the TNB sub-station had been completed. The Contractor had also completed assembling the formwork and steel reinforcement for the columns, which currently awaiting to be cast.
  • General site excavation to finished ground level was in progress.