Sunday, February 28, 2010

The Work Progress as at 28th February 2010


The progress of work for the month ws generally poor, which was partly due to long Chinese New Year holidays and the obstruction caused by the presence of the 200 mm dia. temporary water supply pipeline belonging to the neighbouring housing developer. Mobilisation of heavy equipment for the roadwork and general site earthwork was delayed.

The external and internal plastering of walls of the Shrine hall had completed. However, the construction of roof was still in progress. Assembling of timber purlins to the roof trusses was slow. The Contractor had anticipated the delivery of the roof tiles to Site to be in early March.

The Contractor continued the construction of site fencing and drainage where the locations were freed from obstruction.

The overall progress was about 60%.