The Work Progress as at 30th April 2010

Buddha Image was delivered on 5th April. The 9-foot tall image was unloaded infront of the Shrine Hall and was awaiting installation.

The roof of Shrine Hall was completed. The internal finishing was awaiting the interior designer to complete her proposal.

The Contractor had proceeded with the construction of the roadwork and car park. However not much progress could be achieved with the temporary water supply pipeline belonging to the housing developer still in the way.

Overall progress at the end of the month was about 68%.