Thursday, July 8, 2010

The Work Progress as at 30th June 2010



The work on site was relatively slow and was almost at stand still, except for some installation work carried out inside the Shrine hall.

The plaster ceiling in the Shrine hall was completed at the end of the month with all the lighting fixed. Installation of the distribution board was in progress. All the air-conditioning units had also been installed.
Other minor activities in progress includes fixing of hand railings around the perimeter of the Shrine hall and the compound fencing.

The overall progress was about 77%