The Work Progress as at 31st August 2010







Activity on site was generally low.
Main obstruction to progress in the infra was the housing developer's water pipe, which was finally removed on the 12th August. This enable the construction of the main gates and the front perimeter fence to proceed.

The tiling of the floor of the Shrine Hall commenced on 12th August and was about 90% completed. Tiling the altar with marble tiles was also in progress.

Inspection of the TNB substation by the authority was made on 26th and was given a general approval.

Discussion with the Architect on the design of Block B was in progress. A preliminary layout of the proposal was submitted for review and comment.