Wednesday, December 2, 2009

Work in Progress as on 31st November 2009

The Site was generally wet through out the month and the weather had slowed down the construction. The Contractor managed to complete the concrete structure of the Shrine Hall building and the TNB substation towards the end of the month.

The construction of the TNB substation brick walls had just started and the Shrine Hall was awaiting its roof truss to be assembled.

The work progress was at approximately 40% complete.