Thursday, January 18, 2018

2018 Buddha Puja and offering to the Devas

Buddha Puja and offering to the Devas:
Date : 24 Feb 2018
Venue : Bodhi Park Shah Alam

You are welcome to join and participate in this programme. For your contribution and support, pls contact our headquarter in Penang for further details.

129, 1st Floor, Jalan Seang Tek, 10400 Penang.
Tel: +604 2287146 or +60 19 418 7146
email : ybbmhq@gmail.com









Tuesday, August 29, 2017

2017/08/29 - YBBM goes WhatsApp 马佛基金会联络管道

With effect from 29/07/2017, you may contact YBBM via WhatsApp.

Our new contacts are as follow:


update 22/01/2018

Friday, December 3, 2010

First Activity in Bodhi Park































The Shrine Hall was substantially completed with electric supply on time for the first novitiate programme to be successfully carried out on 20th ~ 28th November 2010 with the shrine hall facility. There were about 10 samaneras and 10 upasikas took part.






Tuesday, August 31, 2010

The Work Progress as at 31st August 2010







Activity on site was generally low.
Main obstruction to progress in the infra was the housing developer's water pipe, which was finally removed on the 12th August. This enable the construction of the main gates and the front perimeter fence to proceed.

The tiling of the floor of the Shrine Hall commenced on 12th August and was about 90% completed. Tiling the altar with marble tiles was also in progress.

Inspection of the TNB substation by the authority was made on 26th and was given a general approval.

Discussion with the Architect on the design of Block B was in progress. A preliminary layout of the proposal was submitted for review and comment.













Monday, August 2, 2010

The Work Progress as at 31st July 2010

Not much activity was carried out on Site during the month. In the early period of the month, the Contractor spent time in getting the ceiling of the Shrine Hall painted and minor preparatory work for the Buddha Image installation.



The Buddha Image was stored in the open, outside the Shrine Hall for a couple of months since its delivery and had been patiently awaiting the hall to be ready.



Installation of the Buddha Image commenced on the 19th July 2010 afternoon with the help of two heavy machinery. The Contractor and the nearby devotees finally managed to place the Image up on the altar by 9.00pm that day.



Positioning of the Buddha Image on the altar continued the next morning with the presence of Chief monk, Ven. Saranakara and his monks from the Sentul Temple. A brief puja was subsequently conducted by the monks followed by dana given by the devotees.


































































Thursday, July 8, 2010

The Work Progress as at 30th June 2010



The work on site was relatively slow and was almost at stand still, except for some installation work carried out inside the Shrine hall.

The plaster ceiling in the Shrine hall was completed at the end of the month with all the lighting fixed. Installation of the distribution board was in progress. All the air-conditioning units had also been installed.
Other minor activities in progress includes fixing of hand railings around the perimeter of the Shrine hall and the compound fencing.

The overall progress was about 77%

Friday, June 4, 2010

The Work Progress as at 31st May 2010


The Contractor had completed laying of the aluminium foil underneath the tiled roof inside the Shrine Hall in preparation for the construction of the plaster ceiling.


All lighting locations were finalised, The wiring and lighting points were installed based on the Interior Designer's proposal.

The Contractor commenced installation of the external ceiling of the Shrine Hall and was completed before the endof the month.



The structure for the Buddha Image altar was constructed and awaiting finishing work to commence.




The infra- structure work comprising the road, car park and fencing was still progressing and was about 40% complete. The progress in the infra-structure work was still affected by the housing developer's water pipeline.

The overall progress was about 70%